Water Treatment Plant

Our Business

Water Supply

Water Treatment Plant, Water Pipe Installation


Water Supply

Water Treatment Plant

Water Supply

Concession Agreement signing ceremony for water supply project (Sandin )Vientiane Capital, On 16 Dec 2015

Phase 1

Production Capacity of Water Treatment Plant 24,000 m3 / day
Phase 2
Production Capacity of Water Treatment Plant 24,000 m3 / day
 
Total Production Capacity = 48,000 m3 / day
 
News on CA signing Ceremony for Construction of Water Plant
 

OPENING  CEREMONY  2 JUNE  2018  by The  Governor  of  Vientiane  Capital

 
 

OPENING CEREMONY 2 JUNE 2018 by The Governor of Vientiane Capital

 
 
 

 

 

VIENTIANE TIMES NEWS


Sandin water supply Project

 

PROGRESS OF CONSTRUCTION SANDIN WATER SUPLY PROJECT

PHOTOS OF TRANSPORTATION WATER PIPE FOR DONGMAKKHAI WATER SUPPLY PROJECT

 

TAP WATER PIPE INSTALLATION


 

 

COMMERCIAL CONTRACT SIGNING CEREMONY WATER PIPE EXTENSION PROJECT IN VIENTIANE CAPITAL


 

March 31, 2016 Commercial Contract Signing Ceremony
On Water Pipe Extension Projectin Vientiane Capital
With Nampapa Nakhone Luang (NPNL)
 

GROUND BREAKING CEREMONY


 

12th October 2016
Ground Breaking Ceremony, Water Pipe System Extension and
Improvement of System Management Project in Vientiane Capital
 

PIPE EXTENSION ZONE DISTRICT METERING AREA (DMA)


 

 

SCHEMATIC DIAGRAM FOR DISTRIBUTION SYSTEM


 

 

PIPE EXTENTION WITH ELEVATED TANK


 

 
Grand total project cost is 100,000,000 U$D
 
DIP pipe DN700 installation
 

ELEVATED WATER TANKS


 

Location : No1 atVernkham
Capacity : 1,000 m3, Height = 34 m.
 

ELEVATED WATER TANKS


 

Location : No 2 at Nanga
Capacity : 1,000 m3, Height = 34 m.
 

ELEVATED WATER TANKS


 

Location : No 3 Songkhauo Kangsan Village
Capacity : 1,500 m3, Height = 34 m
 

KOK HAE WATER TREATMENT PLANT 1,000 CU.M/D


 

 
 

NA LONG WATER TREATMENT PLANT 1,500 CU.M/D


 

​​